Plan Your Exterior Improvement
Aliana’s Design Review process helps preserve the beauty, consistency, and property values of our community.
Approval is required before any exterior work starts. Wait for written approval before starting your project.
1. Prepare Your Application
Find the forms in TownSq > Tools > Documents > Architecture. Include:
- A lot survey showing the proposed location
- Plans and drawings
- Photos of the existing property and proposed changes
- Color and material samples and descriptions
Submit through TownSq > Requests > Architectural Review. For assistance, contact servicedesk@alianaliving.com or Brenda Nieto, Assistant Manager, at assistantmanager@alianaliving.com.
2. Allow Time for Review
The review period is 45 calendar days after the application is complete, under DCCRs Article VI, Section 3. If the committee does not respond within that period, the application is deemed denied.
3. Follow Your Approved Plans
An approval lapses if construction has not substantially started within six months, or if the plans change materially.
Homeowners are responsible for obtaining their own applicable Fort Bend County permits. Verify requirements with the Fort Bend County Engineering Department.
If Your Application Is Denied
You may request a Board hearing in writing within 30 days of the denial letter, under Texas Property Code 209.00505(e). Use the Board Hearing and Appeal Request Form. Contact servicedesk@alianaliving.com for help locating the form.
Guidelines and Forms
Review Aliana’s DCCRs and architectural guidelines when planning exterior paint, roofing, fencing, landscaping, additions, patios, or other exterior work. The documents below provide project requirements and application resources.
servicedesk@alianaliving.com
281-207-6750 • Option 1: The Club at Aliana • Option 2: The Westmoor Club